Analysis of the measurement points

From January to March 2014, "Unison Group", in conjunction with a network of PC PRCE, checked supplied electricity in Bishkek for compliance with the requirements of national standard indicators, and in May 2014 the same work commenced in the towns of Naryn and Kant. The duration of a single measurement is 7 days, including working days and days offs.

When selecting areas to measure the quality of electricity, some regions were better than others because energy companies had reconstructed or upgraded equipment in 2013-2014. This information was taken from the official websites of "Severelectro» (www.severelectro.kg) and JSC "NES Kyrgyzstan» (www.energo.kg).

The measurements were made by electricity quality loggers PE-01, who were certified by the authorised bodies, registered and verified for compliance with the benchmarks.